What to inspect before you accept the keys, in the order that works on the day, by Shivani Mathur.

Read Time7 min read
ByShivani Mathur
ExpertiseVastu · 20 Yrs
UpdatedNovember 2026
New flat possession and snagging checklist guide cover with a checklist illustration
Inspect before you sign. Snags are cheaper to fix before you move in.
Quick answer

Before accepting possession, check the documents first, then inspect the unit in a fixed order: common areas, walls, ceilings and floors, doors and windows, bathrooms and kitchen, and electrical. Mark each snag, photograph it, list it in writing and ask the builder to fix it. Plan your interiors in parallel so the work can start soon after handover.

  • Check the possession letter, occupancy certificate and plan before the unit
  • Inspect in a fixed order and mark each snag with tape and a photo
  • Test every tap, drain, switch and window, do not just look
  • List snags in writing; keep copies of everything
  • Plan interiors before handover so the work starts in the right order
Scope of this guide

DesigningAxis offers interior design and Vastu consultancy. This is a general inspection checklist, not legal, structural, RERA or valuation advice. We do not inspect structures or certify construction. For legal rights, approvals and defects, speak to your lawyer and, if needed, a qualified inspector or engineer. Rules and timelines differ by state, so check with the authority.

Why a snagging inspection matters

Snagging means finding the small defects in a new flat before you accept it: a crack, a leaking tap, a door that does not close. Most builders expect some snags and will fix them. But once you have taken possession and moved your things in, it gets harder to ask.

A careful inspection also helps your interior plan. Before a carpenter makes a wardrobe, you want to know the walls are level and the wiring is where the drawing says. A hidden damp patch behind a future kitchen unit is much cheaper to find now.

Try to go with a second person, in daylight, with a torch, a phone, a plug tester, a tape measure and a roll of masking tape.

Step 1: Documents before the unit

Start with paper. Ask to see these before you look at the flat, and keep copies.

Your lawyer should read the possession letter before you sign. If a letter asks you to give up rights to claim defects, take advice first.

Step 2: The inspection route

Work in the same order each time, so nothing is missed. Mark each snag with masking tape and photograph it with something for scale.

Possession-day inspection route: documents, common areas, walls ceilings floors, doors windows, bathrooms kitchen, electrical
Work through the list in order. Mark each snag with tape, then photograph it.

Step 3: Outside and common areas

These areas are shared, but they tell you how well the project is being handed over.

Step 4: Walls, ceilings and floors

Ceiling height matters if you plan a layered ceiling. Read our False Ceiling Design Guide before you decide.

Step 5: Doors and windows

Step 6: Bathrooms and kitchen

Wet areas cause the most trouble later, so spend the most time here.

Step 7: Electrical

If you plan a modular kitchen or a wardrobe with lights, note exactly where you need extra points. It is much cheaper before the walls are finished. Read the Kitchen Design Guide for what a kitchen needs.

Step 8: Record and follow up

Illustrative plan with numbered hotspots where snags commonly hide: windows, walls, sink, bathroom floor, balcony door, ceiling, switches
Common snag hotspots. Illustrative plan, not a real unit.
SeverityExamplesWhat to do
Must fix before acceptingLeaks, no water, unsafe wiring, non-working lift, wide structural cracksDo not accept until fixed or you have a clear written commitment and legal advice
Fix within an agreed listDoors that rub, loose tiles, patchy paint, minor leaksList with photos, agree a date in writing
CosmeticSmall scratches, minor paint marksNote it; fix at your own time

Send the snag list by email and keep the reply. Under RERA, a buyer can report a structural defect within five years of possession and the promoter is required to fix it within 30 days at no cost to the buyer (Section 14(3)). Details and remedies are for your lawyer to confirm.

After you accept: plan the interior in the right order

If you have planned in advance, the work can start soon after handover. A common order is: measurements, electrical and plumbing changes, false ceiling, wall finishes, flooring changes, carpentry, painting, fixtures, lights, then curtains and furniture. Doing it in a different order often means redoing work.

Read How to Check Vastu Before Buying a Flat if you have not bought yet, or the Complete Vastu Guide for New Homes for the layout once you are in. For the order of work, see our HomeBook Planning Checklist.

Modern living room interior with sectional sofa and layered ceiling lighting
Next guideComplete Vastu Guide for New HomesPlan the layout of a new home room by room.
U-shaped kitchen with pendant lights and a breakfast counter in Shastri Nagar, Ghaziabad
PlanningHomeBook Planning ChecklistThe order of work from measurements to move-in.

Possession-day checklist

Documents

Unit

After

Frequently Asked Questions

What is snagging?

Snagging is the process of finding small defects in a new flat before you accept it, such as cracks, leaks, loose tiles and non-working points. You list them in writing and ask the builder to fix them.

Should I take possession before the snags are fixed?

Minor snags can be listed and fixed with an agreed date. Serious issues such as leaks, unsafe wiring or structural cracks should be settled first or covered by a clear written commitment, with your lawyer's advice.

How long do I have to report defects after possession?

Under Section 14(3) of RERA, structural defects reported by the buyer within five years of possession are to be fixed by the promoter within 30 days at no extra cost. Confirm how it applies to you with your lawyer.

Do I need the occupancy certificate before possession?

Reports say UP RERA now expects possession letters to follow the occupancy certificate. Ask for a copy of the OC and check with your lawyer and the UP RERA website.

Can you inspect the flat for me?

We are interior designers and Vastu consultants, not structural inspectors. We can look at layout, point positions, ceiling heights and finish with you and plan the interior. For structural questions, use a qualified engineer.

When should I start planning the interior?

Before possession if you can. With the approved plan, you can settle the layout, lighting points, storage and materials, then confirm every measurement on site at handover.

Can you plan my interior before I get the keys?

Yes. Send the approved plan on WhatsApp for an online review. We confirm all dimensions on site after possession, before any carpentry is made.

Planning the Interior of a New Flat?

Send your approved plan with north marked. Shivani Mathur plans layout, lighting and Vastu before handover, on site across Delhi NCR or online anywhere in India.

Book a Consultation WhatsApp →